Eisenhower
Memorial Tunnel

The Eisenhower Memorial Tunnel was first called the Straight Creek Tunnel, a name derived from the valley where the west portal was located. The Colorado State Legislature chose the new title in 1972. Dedication of the first of the twin tunnels came March 8, 1973, and the project was opened to two-way traffic on that day. Users of Colorado highways and those of other states provided the financing through state and federal road use taxes. Federal aid accounted for about ninety two percent of the $108 million needed, administered through the Federal Highway Administration. The rest was state funding. Prime contractor for the mile and seven-tenths project was a joint venture, Straight Creek Constructors. Venture members were Al Johnson Construction Company (Minneapolis), Gibbons and Reed Company (Salt Lake City), Kemper Construction Company (Los Angeles), and Western Paving Company (Denver). At the height of activity as many as 1,140 persons were employed in three shifts, twenty four hours a day, six days a week

VENTILATION CONSTRUCTION FACTS: One million cubic yards of material was cleared from each bore. 190,000 cubic yards of concrete was used for each tunnel lining. Three fatalities occurred on the 1st bore six on the 2nd bore. Problems in the Loveland fault area led to drastic measures. The solution was multi-drift construction technology with concrete being pumped continuously so no cold joints would be in the drifts. Outside face to outside face of ventilating buildings is 8,941 feet or 1,693 miles. Of the distance, there are 7,789 feet of rock tunneling and total of 1,152 feet of ventilating/portal structures and cut-and-cover sections at east and west ends. Saving in mileages as compare to the routing over Loveland Pass is 9.1 miles